The twentieth Project Executive Board (PEB) Meeting of CFGORRP/DHM was held on September 15, 2017 under the Chair of Dr. Rishi Ram Sharma, Director General-DHM/National Project Director-CFGORRP. DG from DNPWC; DDGs from DWIDM and DHM; representatives from MoFALD and DSCWM; DCD, ACD and Interim CCPA from UNDP Nepal attended the meeting.
Mr. Top B Khatri, National Project Manager made a detailed presentation of project progress made during the two elapsed quarters (second and third) 2017. He also shared the revised Annual Work Plan of 2017 and summary of asset handover list. After discussions and deliberations, the members endorsed revised Annual Work Plan 2017 and decided to proceed for handover of equipment and furniture to the respective collaborating partners in regard of District Project Offices. Decision for handover of FCO has been postponed in view of the upcoming Terminal Evaluation including completion and handover of activities to stakeholders.